Network Code on Demand Response (NC DR upcoming)
The upcoming Network Code on Demand Response will establish EU-level rules to enable the full participation of demand-side resources in electricity markets. It is currently
The upcoming Network Code on Demand Response will establish EU-level rules to enable the full participation of demand-side resources in electricity markets. It is currently
Commission Regulation (EU) 2016/631 establishing a network code on requirements for grid connection of generators, establishes harmonised connection rules for power-generating modules. The code defines
Commission Regulation (EU) 2016/1388 establishing a Network Code on Demand Connection establishes harmonised requirements for grid connection applicable to any new demand connection to the transmission
Commission Regulation (EU) 2016/1447 establishing a network code on requirements for grid connection of high voltage direct current systems and direct current-connected power park modules. HVDC
Commission Regulation (EU) 2017/1485 establishing a guideline on electricity transmission system operation sets harmonised rules for TSOs, DSOs and SGUs (significant grid users), in order
Commission Regulation (EU) 2017/2196 establishing a network code on electricity emergency and restoration, sets out rules for the management of the transmission system in case
The FCA GL governs the allocation of long-term transmission rights (LTTRs) between bidding zones, enabling market participants to hedge against price differences across borders. Latest
The EB GL harmonises rules for electricity balancing across the EU. It introduces a common framework for balancing energy markets, procurement, and settlement, supporting real-time
The CACM GL establishes rules for day-ahead and intraday market coupling across the EU. It is central to the operation of single electricity markets and